ABSTRAK


PT ABC bergerak di bidang industri manufaktur memproduksi herbisida selektif

sediaan cair. PT ABC memiliki dua bagian dalam departemen produksi yaitu

bagian formulasi dan repack. Permasalahan yang sering terjadi adalah proses

repack herbisida kemasan 40 mL mengalami kehilangan herbisida dan pelaporan

output WIP setiap akhir shift tidak direkam secara baik oleh operator. Sejak bulan

Januari sampai Juni 2023 terjadi kehilangan herbisida sebanyak 249 liter atau

1,42% dimana ini melebihi batas maksimal kehilangan herbisida sebesar 1%.

Penelitian ini bertujuan untuk mengidentifikasi waste pada proses repack

herbisida kemasan 40 mL beserta faktor penyebab terjadinya, serta usulan

perbaikan dengan menggunakan pendekatan Lean Manufacturing. Penelitian

diawali dengan pengumpulan data, seperti alur proses, waktu prores, observasi

dan wawancara Brainstroming. Selanjutnya dilakukan pemetaan aliran ptoses

menggunakan Value Stream Mapping (VSM) dan Process Activity Mapping

(PAM). Lalu dilakukan identifikasi waste dan faktor penyebabnya menggunakan

diagram fishbone. Setelah diketahui waste dan penyebabnya, dibuatkan usulan

perbaikan guna meminimasi waste. Jenis waste yang teridentifikasi adalah

penggunaan bahan baku berlebih dan proses tidak tepat (inappropriate

processing) dengan faktor penyebab utama tercecernya herbisida saat proses

transfer ke hopper akibat penggunaan handpump dan kesalahan hitung saaat

proses menghitung WIP yang dilakukan secara manual. Lalu diberikan usulan

perbaikan mengganti drum dengan IBC yang diberikan dudukan serta adaptor

keran sesuai desain, pengadaan sensor hitung otomatis, pengadaan papan untuk

penyusunan WIP, serta APD, pelatihan dan sosialisasi SOP untuk menunjang

kinerja operator.

Kata kunci: herbisida, repack, lean manufacturing, value stream mapping,

process activity mapping, fishbone


ABSTRACT


PT ABC is engaged in the manufacturing industry producing liquid selective

herbicides. PT ABC has two sections in the production department, namely the

formulation and repack sections. The problem that often occurs is that the process

of repacking 40 mL herbicide packages experiences loss of herbicide and the WIP

output reporting at the end of each shift is not recorded properly by the operator.

From January to June 2023 there was a herbicide loss of 249 liters or 1.42%,

which exceeds the maximum herbicide loss limit of 1%. This research aims to

identify waste in the 40 mL herbicide repack process along with the factors

causing it, as well as suggestions for improvements using the Lean Manufacturing

approach. The research began with data collection, such as process flow, process

time, observation and brainstorming interviews. Next, process flow mapping is

carried out using Value Stream Mapping (VSM) and Process Activity Mapping

(PAM). Then identify waste and its causal factors using a fishbone diagram. After

knowing the waste and its causes, proposals for improvement are made to

minimize waste. The type of waste identified is the use of excess raw materials and

inappropriate processing, with the main factors being the spillage of herbicide

during the transfer process to the hopper due to the use of a handpump and

calculation errors during the manual WIP calculation process. Then

recommendations for improvements were given to replace the drum with an IBC

which was provided with a stand and tap adapter according to the design,

procurement of automatic counting sensors, procurement of boards for preparing

WIP, as well as PPE, training and dissemination of SOPs to support operator

performance.

Keywords: herbicide, repack, lean manufacturing, value stream mapping, process

activity mapping, fishbone